Services Provided
- Conduct analysis on current situation and plans included topographical surveys and soil investigations;
- Perform major hydraulic engineering investigations and planning; review and approve layout and design of drainage and flood control engineering;
- Develop design outline, Detailed Engineering Design (DED) and Cost Estimation& Tender Documents;
- Conduct survey and LARAP investigation (reference used to OD’s World Bank no. 4.01)
- Conduct social and livelihood analysis;
- Plan, organize, assign, and supervise personnel in the development and operation of flood control and water conservation sub-projects;
Project Summary
Name of Client: Badan Rehabilitasi dan Rekonstruksi NAD – NIAS (BRR)
Project Name: “Infrastructure Reconstruction Enabling Program IREP No.3, Nias Infrastructure and Services Planning, Design, and Construction Supervision (Nias PDCS), funded by the World Bank”
Location: Nias District, North Sumatera